The operation points of the air classifier
In the ultra-fine classification equipment, the main product is the air flow classifier. It is necessary to understand the basic operation of the air flow classifier.
1. Before starting the equipment, check the connection parts, seals and wiring, etc., and start operation only after all checks are correct.
2. The power-on operation should be performed in accordance with the power-on sequence. 3 minutes before shutting down, stop feeding, and then shut down again, the order is opposite to the order of starting up.
3. The feed volume should be determined according to the load of the main engine to ensure that the main engine is under the rated load.
4. The fineness of the separated particles can be adjusted to meet the classification requirements.
5. If it is to separate heat sensitive materials, the power of the main motor should be slightly lower than the rated power.
6. The size of the air volume in the conveying pipeline can be realized by adjusting the air door of the fan.
7. The tension of the belt should be checked to prevent belt slippage.